This was the 3rd CER that Equiptec has built for Imperative Care Inc (ICI). ICI required a 3,500 sqft CER to manufacture different parts of their product with an additional 1,000 sqft CER that has humidity control.
Equiptec demoed the existing space and provided 1" thick concrete subfloor repair throughout. All HVAC units were removed and replaced with new.
The CERs were built with a large Gowning Room, Combine Material Transfer Room, Large CER and Small Humidity Controlled CER with Touchless Automatic Sliding doors w/ Interlock System, Electronic Magnenelc Gauges measuring the pressure In each room to ensure proper pressure cascade.

Celestica Rincon Anodizing Line
March 2022
Client: Celestica
Industry: Anodizing, Machining, Part Manufacturing


Equiptec self preformed or subcontracted all electrical, mechanical, plumbing, and architectural construction as well as managed the activities of their boiler contractor and process equipment manufacturers.
The scope of work included: construction of new offices, process laboratories, and chemical treatment area; construction of a multi thousand square foot structural steel support frame for roof mounted equipment; enlarged concrete footings and support columns to carry the increased load from (4) new 40 ton roof mounted chillers; demolished, excavated, and poured a new 1,400 sq. ft. concrete equipment pad with roof structure and slatted chain linked fence enclosure to house 2 new gas fired process boiler.
And provided welded steel boiler piping to new heated process tanks and provided thermal plastic interconnect piping from the new chillers to temperature controlled anodizing and rinse tanks; installed low pressure air blowers to provide agitation in rinse tanks; fabricated a thermal plastic cda piping distribution system; provided chemical resistant epoxy flooring throughout the process areas; provided portable welded steel forklift ramp and pallet racking in the new shipping and receiving area.
Celestica engaged Equiptec as the prime contractor to coordinate, manage, and implement the installation of a new anodizing line for a critical and time sensitive contract with one of their clients at their 950 Rincon Facility.
Services Provided: Process piping, Roof SuperStructure, Chiller Installation, Boiler Installation, Chiller Piping, Boiler Piping, Power Upgrade, Gas Upgrade, Framing, Drywall, Doors, Concrete Foundations, Concrete Stem Walls, Shipping Receiving Ramp, Epoxy, Chemical Containment Berms, Raised FRP Grating, Utility Trench, Equipment Pad, CMU Walls, Fire Sprinkler, Structural Steel Modifications, Cleanroom Modifications, Exterior ADA Upgrades, Crane Install
Client testimonials
"Our team has worked with Equiptec for more than 10 years on many projects, from existing facility updates to full buildouts of new facilities. Most recently we partnered with them on the buildout of our new corporate headquarters. The Equiptec team prides themselves on the quality of their work and brings strong sub-contractor relationships to the table that resulted in a beautiful, functional facility that we are proud to call our new home."
Carole Roth
Imperative Care

Client testimonials
"Equiptec is our trusted partner when it comes to everything related to our buildings and construction. I put them to the test on a large restructuring and lease restoration project and they passed with flying colors. Reliable, Professional and On time."
David Springsteen
Celestica

Client testimonials
"Working with Equiptec over the last 18 years has been a great experience. They not only meet their customers needs but exceed their expectations. Equiptec brings experience and technical know how to problem solve complex issues while maintaining strict budgetary discipline. They are truly one of the top contractors servicing the Bay Area."
Ryan Balzer


We build with integrity to create spaces that elevate
people's lives, work, and futures.