Process and Production Facilities

Equiptec has extensive experience in design and construction of manufacturing environments for R&D, prototyping, pilot and production facilities. These include processes requiring large quantities of hazardous materials including H6 and H7 occupancies.

Celestica-Logo.wine.png

Project Spotlight

Celestica Rincon
Anodizing Line

Date: March 2022

Client:  Celestica

Industry: Anodizing, Machining, Part Manufacturing

Services provided: Process piping, Roof SuperStructure, Chiller Installation, Boiler Installation, Chiller Piping, Boiler Piping, Power Upgrade, Gas Upgrade, Framing, Drywall, Doors, Concrete Foundations, Concrete Stem Walls, Shipping Receiving Ramp, Epoxy, Chemical Containment Berms, Raised FRP Grating, Utility Trench, Equipment Pad, CMU Walls, Fire Sprinkler, Structural Steel Modifications, Cleanroom Modifications, Exterior ADA Upgrades, Crane Install

Description and objective

Celestica engaged Equiptec as the prime contractor to coordinate, manage, and implement the installation of a new anodizing line for a critical and time sensitive contract with one of their clients at their 950 Rincon Facility. Equiptec self preformed or subcontracted all electrical, mechanical, plumbing, and architectural construction as well as managed the activities of their boiler contractor and process equipment manufacturers.

The scope of work included: construction of new offices, process laboratories, and chemical treatment area; construction of a multi thousand square foot structural steel support frame for roof mounted equipment; enlarged concrete footings and support columns to carry the increased load from (4) new 40 ton roof mounted chillers; demolished, excavated, and poured a new 1,400 sq. ft. concrete equipment pad with roof structure and slatted chain linked fence enclosure to house 2 new gas fired process boilers; provided welded steel boiler piping to new heated process tanks and provided thermal plastic interconnect piping from the new chillers to temperature controlled anodizing and rinse tanks; installed low pressure air blowers to provide agitation in rinse tanks; fabricated a thermal plastic cda piping distribution system; provided chemical resistant epoxy flooring throughout the process areas; provided portable welded steel forklift ramp and pallet racking in the new shipping and receiving area.

anodizing line 1.jpg
950-Rincon-Circle---San-Jose_D4W0582_HDR.png
CER8.jpg
Anodizing-Line.png
Anodzing line w_ Crane (Blur Ronatec).jpg
anodizing-line-1.png